Smart Stations

Services

Capacity for growth
Capacidad de crecimiento
Safety in your design
Autonomous operational operation
Explosion- and impact-proof equipment
Mobile Station (moveable)
Complies with NOM 005 ASEA 2016
A partir de 420 m² de terreno

IT CONSISTS OF 4 MODULES

01
Administration module.
03
Clean warehouse module, dirty room, hazardous waste room.
02
Pumping room module.
04
Machine room module.

Project ES-001 70,000 LTS TANK

4 Positions, 2 Products, 1 Dispenser
Construction of the Station
Forms of payment:
5% DOWN PAYMENT ON CONTRACT SIGNING
30% WHEN RECEIVING A BUILDING LICENSE
30% AFTER 60 DAYS
25% AFTER 20 DAYS
10% IN OPERATIONAL TESTS
Management of procedures and permits
Forms of payment:
5% DOWN PAYMENT ON CONTRACT SIGNING
30% WHEN RECEIVING A BUILDING LICENSE
30% AFTER 60 DAYS
25% AFTER 20 DAYS
10% IN OPERATIONAL TESTS

Project ES-002 70,000 LTS TANK

4 Positions, 2 Products, 2 Dispenser
Construction of the Station
Forms of payment:
5% DOWN PAYMENT ON CONTRACT SIGNING
30% WHEN RECEIVING A BUILDING LICENSE
30% AFTER 60 DAYS
25% AFTER 20 DAYS
10% IN OPERATIONAL TESTS
Management of procedures and permits
Forms of payment:
5% DOWN PAYMENT ON CONTRACT SIGNING
30% WHEN RECEIVING A BUILDING LICENSE
30% AFTER 60 DAYS
25% AFTER 20 DAYS
10% IN OPERATIONAL TESTS

Project ES-003 90,000lts TANK

6 Positions, 2 Products, 3 Dispenser
Construction of the Station
Forms of payment:
5% DOWN PAYMENT ON CONTRACT SIGNING
30% WHEN RECEIVING A BUILDING LICENSE
30% AFTER 60 DAYS
25% AFTER 20 DAYS
10% IN OPERATIONAL TESTS
Management of procedures and permits
Forms of payment:
5% DOWN PAYMENT ON CONTRACT SIGNING
30% WHEN RECEIVING A BUILDING LICENSE
30% AFTER 60 DAYS
25% AFTER 20 DAYS
10% IN OPERATIONAL TESTS

Requirements

You must have:
1.

Land Location

2.

Factability study of the area where it is located (not near schools, churches, etc.)

3.

Land use (Not accepted if residential)

4.

Building license

CONDITIONS

Estimated recovery time after opening: 1 year
Construction time and key delivery:

5 months
(may vary depending on the characteristics of the project)
Local, state and federal procedures are done in parallel
The CRE permission is a variable in terms of time